Posted on: June 5, 2024

[ARCHIVED] Road Repaving - Charland Avenue and Seaforth Crescent

The City's contractor is scheduled to repave the following streets: Charland Avenue, from Decaire Street to the north end; Charland Avenue, from Laurentian Crescent to the east end; and Seaforth Crescent, from the northwest end to Seaforth Crescent.

What: Road Repaving

 

Where: 

  • Charland Avenue, from Decaire Street to the north end; 
  • Charland Avenue, from Laurentian Crescent to the east end; and 
  • Seaforth Crescent, from the northwest end to Seaforth Crescent.

When: Construction is expected to begin the week of June 10.  Work on each street will take about 3 weeks to complete.  Crews will work Monday to Friday between 7:00 a.m. to 7:00 p.m. They may work some Saturdays as well.

 

Traffic Impacts: Traffic flow and street parking will be impacted during certain phases of construction, but every effort will be made to minimize the disruption. 

 

For more information, contact:
Public Works Liaison 
604-927-3550